Progress

On Monday 4 March 2024 there was a joint meeting between VRG/CVDCC. The Community Hall was unanimously approved, and work is now progressing with regard to planning permission etc. 

The change of the name from Meeting Room to Community Hall is for VAT tax purposes. Shirley Paterson will be doing an EPC survey for the new building.

Community Wide Consultation 

On 9th September 2021 a Consultation mailing was sent to all households within VRG’s mailing list.  The results are now in and can be viewed here:

Consultation results

There were 85 respondents to the consultation with 81% (69) in favour of proceeding with the meeting room project and 19% (16) against. 

Next steps as per chart below.

Further Information

If you have any questions or would like further information please get in touch with Helen Bang, Admin Assistant.

PROJECT TEAM

Community Meeting Room Subgroup: Rob Ferguson, Dorothy Breckenridge, Susan McPhee, Margaret Porter, Gordon Berry, Maureen Berry, Amanda Smith, Dugald Macalpine. 

Project DOCUMENTS

SUMMARY PROJECT PLAN

REPORT TO CVDCC AND VRG BOARD

PROGRESS REPORT NO 1

PROGRESS REPORT NO 2

PROGRESS REPORT NO 3

PROGRESS REPORT NO 4

PROGRESS REPORT NO 5

PLANNING DOCUMENTS

20005-Existing Block Plan

20006-Proposed Block Plan

20007-Proposed Site Plan

20020-Proposed Floor Plan

20030-Proposed Elevations

A1550 – Design Statement_compressed

 